Saronbrug - Surinam

Delivery of a 225 meter long double lane truss bridge in 3 spans of each 75 meter, incl 2 side external pedestrian walk ways.

The bridge was designed and produced in The Netherlands and shipped to Surinam. A local contractors installed the bridge and the concrete deck.

 

Deel op:

Projectdetails

Oplossing
Vakwerkbrug
Type
JTB
Klant
Ministry of Public Works of Surinam
Number of Bridges
1
Bridge Length
225 meter
Bridge width
8 meter
Completed
2014
Vakwerkbrug
  • The Saron bridge was opened on 28 September 2014. 
  • The bridge is 225 mets long and 16 meters wide in total. 
  • The bridge was part of a project that included 1 km of new road and a roundabout. 
  • The bridge has reduced the heavily trafficed Coesewijne bridge.

Uitgelicht

Vakwerkbrug (JTB)
Oplossing

Vakwerkbrug (JTB)